Budimex's Kamelia solar farm reached 14 MW operational capacity, while Azalia solar farm neared its 60 MW target with completion set for 2025. Image Source: Budimex
Spain-based Budimex was completing two renewable energy projects, the Kamelia and Azalia photovoltaic farms, as part of its expansion.The Kamelia farm in Wymysłów, Mazowieckie Voivodeship, started in February 2023, covered 180,000 m² with 33,870 panels of 620 watts each. It had a 21 MW capacity, with 14 MW already operational. Its design allowed effective solar energy use. Completion was planned for March 2025. Energy production was set to begin in June. The Azalia farm in Wysoka Głogowska started in May 2024. It was expected to reach 60 MW with 100,000 panels. The farm was projected to generate 65 GWh annually. Completion was set for mid-2025.Additionally, Budimex aiming to achieve 80 MW in 2025.