India Power generation company SJVN, has reported the commercial operation of 100.56 MW at the Bikaner Solar Power Project in Rajasthan. According to the company, the capacity was commissioned through SJVN Green Energy Ltd, wholly owned subsidiary of SJVN.  As per the company’s disclosure, the commissioning has increased the total operational capacity of the 1,000 MW project to approximately 830.70 MW. This leaves a remaining capacity of about 169.30 MW yet to be commissioned under the project. SJVN indicated that the balance capacity of 169.30 MW was under execution and scheduled for commissioning in subsequent phases. The disclosure was made pursuant to SEBI LODR Regulations, 2015. The company stated that the commercial operation date for this capacity was declared effective December 12, 2020.