Hyderabad-based Bondada Engineering had received a INR 945.10 crore EPC order from NLC India Renewables. The order covered Balance of System (BoS) works for 810 MW solar projects at the RVUNL Solar Park in Bikaner, Rajasthan. The scope included design, engineering, site development, supply, installation, testing, commissioning, evacuation systems, and three years of operations and maintenance. Execution was scheduled within 15 months from acceptance of the letter of award dated December 22, 2025. Following this order, Bondada Engineering’s EPC order book rose to nearly 3 GW, reflecting its role in large-scale utility solar project execution.
Bondada Engineering wins 810 MW RVUNL solar project in Bikaner
An EPC contract worth INR 945.10 crore was awarded to Bondada Engineering by NLC India Renewables for 810 MW BoS works at RVUNL Solar Park, Bikaner.
/solarbytes/media/media_files/2025/12/23/2025-12-23-bondada-pr-2025-12-23-16-43-05.jpg)
Advertisment
/solarbytes/media/agency_attachments/2025/01/13/2025-01-13t112055287z-solarbytes.png)
/solarbytes/media/agency_attachments/2025/01/13/2025-01-13t112030439z-solarbytes.png)